City Projects

Water Department Blue Pipe
City public works projects that are currently taking place throughout the city limits. 

 

Bates Ave WWTP Expansion:

The Phase 1 engineering package has been
completed.  Phase 2 Engineering has been awarded, and the team is now in design to provide the construction plans. The engineer and Construction Manager provided a cost estimate that was submitted to City staff and is currently being evaluated. 

Eastern WWTP Transfer Pump Station:

This project will coincide with the reclaim pond lining project.  Construction site crews are almost finished with the installation process on the pump station and will test the new equipment.

Woodward Ave. Improvements:  

Update (6/29/22):

The contractor’s crews is installing sewer pipe between Donnelly St. and Schultz St., along with manholes at several intersections along Woodward Ave. Once completed, the crew will then install storm water piping and structures along Woodward Ave. Project will be completed by fall of 2022. 

If you have any questions or concerns you may call Mike Brisson, City of Eustis Project Manager at 352-483-5460 or email at brissonm@eustis.org

Umatilla Wastewater Interconnection with the City of Eustis:

The City of Umatilla’s contractor completed the installation of the wastewater pipe and fittings in order to make the connection to our Wastewater Treatment Plant. Currently, the crew is working on the electrical and will resurface the roads and curbs on Pinkney St., Hollywood Ave., and Bates Ave. 

 

View a list of development/planning projects that are taking place in the City.

Development/Planning Projects