Planned Night Work Along SR-19

Published on May 08, 2025

Planned Night Work Along SR-19 will take place between May 11 - 22 of 2025.

Duke Energy will be continuing transmission line work on SR-19. Night work is planned between the weeks of May 11 - May 22. Both lanes will remain open during the day.

 

The schedule of work includes: 

  • Week of May 11: 
    Night work activities will include excavation and pole installation in the general area of SR-19 near E Badger Ave. and E Ward Ave. 
  • Week of May 18:
    Continued excavation and pole work expected to occur in the vicinity of SR-19 near E Key Ave. and E Lemon Ave. 
  • Later in the week of May 18 into May 22:
    Additional work may include framing of structures along portions of SR-19 between E Badger Ave. and E Lemon Ave.